Referencing a Business Process from another Business Process

To pass data from one Business Process to another, reference the second Business Process as a task in the first Business Process.

You must have two Business Processes created:
  • The one you want to initially use (Initial Business Process)
  • The one to which you want to branch (Branch Business Process)

If it is unclear why you would want to do this, see Business Process.

  1. Open the initial Business Process object's editor.
  2. Under the Script section, click the Add button to add a new task.
  3. Click Click to select task to produce a selection window. Select the Branch Business Process.
    Note: A Business Process must be contained in the current Project or in a Package that has been made available to the current Project to appear in the selector window.
  4. Click the Save button and close the editor to complete this task.
    For more information on defining a Business Process, see Understanding a Business Process.